On Going Projects


Sr NoWorkClientJob StartedDuration
1 Fabrication of Offshore Platform at L&T Hazira L&T MFF, Hazira, Surat 01/03/2013 1 Year 8 Month
2 Shut Down, Cracker Unit RIL Refinery Reliance Petroleum Limited, Jamnagar (Refinery) 01/01/2013 90 Days
3 Piping and Structural Work For ISBL & OSBL HPCL-Mittal Energy Limited (HMEL) 01/10/2012 6 Months
4 AOC, PC Fired Boiler and Associated Work at Power Plant. Essar Project India Ltd, Essar Steel Ltd, Hazira 01/10/2012 1 Year 5 Months
5 Fabrication of a Alloy Steel Piping Spool (IBR & Non IBR) Heavy Schedule. L & T Piping Center, Hazira 01/10/2012 10 Months
6 Fabrication and Erection of Piping and Equipment, Erection for Chemical Units. FLUOR, BASF Dehej. 01/05/2012 2 Year
7 Fabrication and Erecting of Piping & Structural, Erection of Static or Rotary Equipments, Alignment & Allied Jobs. Guru Gobind Singh Refinery Limited, Bathinda Punjab 01/04/2012 2 Year 4 Months
8 Fabrication and Erecting of Storage Tank & Piping Jobs . BOC, IAPA and IG System at DPC, OPaL Dahej. 01/02/2012 1 Year and 6 Months
9 Fabrication and Erecting of Piping & Structural, Erection of Static or Rotary Equipments, Alignment & Allied Jobs. EPIL,ESSAR Oil Refinery, Vadinar 01/01/2012 2 Year and 3 Months
10 Fabrication and Erecting of Piping & Structural, Erection of Static or Rotary Equipments, Alignment & Allied Jobs. L & T Special Steel And Heavy Forgings 01/01/2012 1 Year 6 Months
11 Fabrication and Erecting of Piping & Structural, Erection of Static or Rotary Equipments, Alignment & Allied Jobs. Essar Project India Ltd, IOCL Refinery,Paradeep 01/09/2011 2 Year 6 Months
 

Current News

  • Metal Crafts Entered to O... 05/05/2013

    Metal Crafts have received a prestigiou...
    Read More>>
  • Best Contractor of HMEL 04/04/2013

    Metal Crafts is awarded the best contrac...
    Read More>>

Essar Project India Ltd, IOCL Refinery,Paradeep